MPN Gets Go-Ahead for North Sea Exploration Drilling

Thursday, September 10, 2009

Marathon Petroleum Norge AS (MPN) has been given permission to conduct exploration drilling in the northern North Sea with Songa Dee semisub.


Approval applies to drilling exploration wells 24/9-9 S is part of production license 340. The well has the following geographic coordinates: N 59 degrees 19 '40, 414 ', E 01 degrees 50' 17.110 ". The depth of water at the location is 120 meters.

Drilling is scheduled to begin in September / October 2009. This activity has an estimated period of 36-53 days.

Songa Dee (formerly Stena Dee) is a semisubmersible drilling of the type "Mitsubishi MD-602". That was completed in 1984.